The Challenges

An existing 600 meter pipe conveyor was aged and had to be replaced. A time window of 5 days was available to replace,install 2 vulcanizing joints and replace the tail pulley. Engineering was required as their was no area were the conveyor belt could be removed/re-installed. The only way possible was to cut and area in the existing structure. Detailed engineering was done and all the modifications were executed by FaBa.

Project Description

Client:Aluminium company
Location:Middle East
Year Completed:2010 - 2015